The Novato Boulevard overhaul between Diablo Avenue and Grant Avenue is starting at the bottom. The City of Novato expects construction to begin in late October or early November 2026 and to take about 18 to 24 months. The pipes come first. The continuous sidewalks, bike lanes in both directions, center turn lane and new signals the project has promised since 2001 are scheduled for the end.
If you drive from the Safeway at 900 Diablo Avenue toward downtown Grant Avenue, or bike it, or walk part of it, that order shapes what you will see for most of the next two years. Much of that time goes to work you will never see once it's finished.
Three Layers, From the Bottom Up
Patch reported on October 12 that city staff described the work as three layers, in this order:
- Novato Sanitary District replaces the sewer mains, plus the laterals that run from homes to the trunk line at the center of the street.
- North Marin Water District replaces the water lines and service connections.
- The City of Novato rebuilds the surface: roadway, sidewalks, bike lanes, drainage, signals and lighting.
The Marin Independent Journal reported that the sanitary district is replacing laterals because the infrastructure is old. It also reported that the water district is replacing the lines that serve the houses along the corridor. The underground phases reach out to individual properties as well as running down the middle of the road.
According to North Marin Water District's project page, the district is installing new water facilities between Diablo and Grant and leaving the existing pipelines in the ground for possible future recycled-water use. That could save a future project from digging up the street again.
Why One Contract Instead of Three
The order follows from a decision the three agencies made together. The City says it partnered with North Marin Water District and Novato Sanitary District so that roadway and underground utility work would go out as one construction project. The goals were to improve efficiency, shorten the overall schedule and "minimize repeated disruptions to the community." Novato Sanitary District's board packet gives the same reasoning: combining the roadway and sewer work was meant to save time and money.
Without bundling, the City could repave and stripe a new boulevard only to have a utility cut through it later. With bundling, the finished surface goes down once, on top of the new pipes.
The corridor has already had a long run of construction. PG&E's gas and electric undergrounding along the boulevard is substantially complete, according to the City. Electrical service cutovers, removal of overhead equipment and telecommunications work will continue into 2027. Public Works Director Chris Benigni acknowledged that history at the August council meeting, as the Marin Independent Journal reported:
"It's going to be another 24 months of dirt, dust, noise, and I realize that the community has dealt with a lot as PG&E and the private utilities have been doing their undergrounding work for years now."
In the same remarks, he said the City intends to communicate with the neighborhood better, improve traffic control, reduce disruption and give advance notice of major traffic disruptions.
What the Contract Already Plans for the Messy Middle
The City's bid summary from August 19, 2026, shows that the contract prices in some of the in-between period before the new road exists. It includes a line item for a traffic control system, one for a temporary pedestrian access route, and temporary signal systems at Diablo Avenue and at Seventh Street/Tamalpais Avenue. So the intersections at the Diablo end and in the middle of the corridor are planned to run on temporary signals while the permanent ones are rebuilt. The plan also includes a way through for people on foot.
The City has not published work hours, detour routes or a segment-by-segment schedule. Its October 2026 update says residents, businesses and drivers should expect periodic traffic delays, lane restrictions and temporary changes to access. The same update says the City and its construction management consultant are building a dedicated project information page with regular updates on schedules and traffic impacts. Until that page is live, the City's Novato Boulevard Improvements page is the official source.
The Road That Comes Last, Segment by Segment
The finished boulevard won't be the same along its whole length. On June 12, 2018, the City Council approved what the City calls a "3-lane layout." An earlier concept, documented in a 2010 state environmental filing, had called for four travel lanes. The three-lane label describes the general design, and the lane count still changes from block to block. Near Grant Avenue it reaches three through lanes plus a center turn lane. The City describes the lane setup like this:
| Stretch | Planned lanes |
|---|---|
| Diablo Avenue to Seventh Street/Tamalpais Avenue | One through lane each direction, plus a center two-way left-turn lane |
| Boulevard Terrace to Seventh Street/Tamalpais Avenue | A second northbound through lane added |
| Seventh Street/Tamalpais Avenue to Grant Avenue | Two northbound lanes, one southbound lane, plus a center two-way left-turn lane |
Along the whole corridor, the City lists contiguous sidewalks on both sides and Class II bike lanes on both sides. It also lists updated crosswalks, traffic signals and street lighting, drought-tolerant and fire-wise landscaping, pavement rehabilitation, and upgraded drainage with clean water treatment. Project engineer Elisa Sarlatte told the council, as Patch reported, "We are going to add sidewalks on the portions of Novato Boulevard where there currently are not sidewalks on both sides of the street." According to the same report, new storm drains and bio-retention areas will collect and treat runoff before it reaches local creeks.
The new signals are planned for Diablo Avenue, Seventh Street and Grant Avenue. Those are the same points that anchor the corridor now, from the Diablo end to the Grant end near downtown, where City Hall and the Novato History Museum stand. The City also says it will need to acquire portions of land on the frontage of five parcels, all between Cypress Avenue and Diablo Avenue.
Twenty-Five Years, and What the Money Covers
The Marin Independent Journal reported that planning started in 2001 and the council approved the designs in 2018. City staff told Patch the delays came from environmental review, utility coordination and funding. The Draft Environmental Impact Report went to the State Clearinghouse on October 5, 2021.
Eight bids were opened on August 19, 2026. On September 22, 2026, after a bid protest was resolved, the council awarded the construction contract to Team Ghilotti, Inc. as the lowest responsive, responsible bidder. The construction contract is a little over two-thirds of the estimated total:
| Item | Amount |
|---|---|
| Team Ghilotti, Inc. bid total | $16,824,357.50 |
| Ghirardelli Associates, construction management and inspection, awarded in May | about $2.2 million |
| Total project estimate, including construction, staff time and contingency | about $23.9 million |
The funding is split the same way the digging is. The Marin Independent Journal reported about $8.49 million in Measure AA funds for the City's construction share, about $4.7 million from Novato Sanitary District and an estimated $2.7 million from North Marin Water District. Benigni said those figures could change once bid results are reconciled with each agency's estimates. The City puts its own share, including its estimated part of joint costs such as traffic control, at about $8 million. The sanitary district's sewer bid items came to $4,723,889, which was $149,251 above its engineer's estimate, and the district agreed to cover the difference.
"This is a massive project for the community," City Manager Amy Cunningham said, according to the Marin Independent Journal.
Who to Call While It's Underway
The City lists Novato Public Works at 415-899-8246 and [email protected] for questions about the project. For PG&E work still going on along the boulevard, it lists PG&E Outreach Specialist John Baston at (707) 867-9466. The start dates and the launch of the project page are the City's October 2026 estimates and may change, so check the City's page before planning around a specific week.
If you own a home on or near the Diablo-to-Grant stretch and want to think through how 18 to 24 months of utility and road work could affect timing for a sale, a purchase or a pre-listing renovation, Amadeo Arnal is glad to talk it through with you. Request your complimentary Marin market consultation.